SOP Title: Operation, Cleaning and Calibration of Magnetic Stirrer

SOP Title: Operation, Cleaning and Calibration of  Magnetic Stirrer

  1. Objective:

To lay down the procedure for Operation, Cleaning and Calibration of Magnetic Stirrer.

  1. Scope:

This SOP is applicable for Operation, Cleaning and Calibration of Magnetic Stirrer located in Quality Control Laboratory.

 

  1. Responsibility:
  • Quality Control: To prepare and review the SOP. To follow the procedures laid down for Operation, Cleaning and Calibration of Magnetic Stirrer as per this SOP.
  • Engineering Department: To carry out preventive maintenance as per schedule and procedure defined.
  • Quality Assurance Department: To review and approve the SOP and Annexures.
  1. Accountability:

Head Quality Control Department, Head Quality Assurance Department

  1. Procedure:

 

   5.1 Safety Precautions/Instructions:
5.1.1 Ensure all the electrical connections are properly earthed. Ensure the power plug of the centrifuge apparatus is fixed in the socket properly.  
5.1.2 Ensure that the ON/OFF switch is working properly by switching “ON Magnetic Stirrer.  
5.1.3 Wear personal protective equipments such as safety glasses, hand gloves during operation of equipment.  
5.1.4 Before instrument is put ON check that the speed  and  heat   control  knobs  are in  “0”  position  and  the  corresponding  switches  are  in  OFF  position.  
5.2 Operation:
5.2.1 Check the validity of Calibration before starting any operations.  
5.2.2 Switch ON the main switch of the equipment and then the ON/OFF switch on the equipment.  
5.2.3 The orange light indicator on the equipment will glow.  
5.2.4 Insert the magnetic bid slowly in the sample solution to be stirred.  
5.2.5 Place the sample solution on the equipment at room temperature or at specified temperature on the top flat surface of the equipment approximately in the centre.  
5.2.6 Set the required speed by rotating ‘SPEED’ knob.  
5.2.7 To increase the speed of stirring, rotate the ‘SPEED’ knob in clockwise direction and to decrease the speed of stirring, rotate the ‘SPEED’ knob in anti-clockwise direction.  
5.2.8 If heating is required then set the required temperature on the ‘HEAT’ knob. The red light indicator on the equipment will glow.  
5.2.9 Ensure that there is no spillage of sample solution on the equipment during speed adjustment.  
5.2.10 After stirring is completed, remove the sample solution from the magnetic stirrer.  
5.2.11 Turn off ‘HEAT’ knob and ‘SPEED’ knob by rotating them in anticlockwise  direction and bring at “0” position.  
5.2.12 Switch OFF the ON/OFF switch on the equipment and the main switch.  
   5.3 Cleaning Procedure:  
5.3.1 Disconnect the equipment from the switch.  
5.3.2 Clean the top flat surface with wet cloth to remove debris and finally clean with lint free dry cloth.  
5.3.3 Clean the equipment after use.  
   5.4 Calibration Procedure:
  Frequency:  Once in a year
5.4.1 Calibration is carried out by external agency as per SOP.  
5.4.2 Refer Annexure for calibration test to be performed and acceptance criteria.

Sr. No. Tests Set value Acceptance Criteria
1. Temperature Verification 30oC ±3oC
60oC ±3oC
90oC ±3oC
 
5.4.3 Generate the A. R. No. on the “Instrument/Equipment Calibration Register”  
5.4.4 For issuance of calibration report refer QA SOP.  
5.4.5 If any breakdown occurs, follow procedure as per SOP  

 

  1. Definitions / Abbreviations :
  • Definitions :
  • Abbreviations:
Abbreviation Expansion
SOP Standard Operating Procedure
QC Quality Control
QA Quality Assurance
A. R. No. Analytical Reference Number

 

*Note – Ready to use SOP available in “DOWNLOAD” Section.

 

Leave a Reply

Your email address will not be published. Required fields are marked *

error: Content is protected !!