SOP Title: Operation and Calibration of Micrometer Screw Gauge
- Objective:
To lay down the procedure for Operation and Calibration of Micrometer Screw Gauge.
- Scope:
This SOP is applicable for Operation, Cleaning and Calibration of Micrometer Screw Gauge located in Quality Control Laboratory.
- Responsibility:
- Quality Control: To prepare and review the SOP. To follow the procedures laid down for Operation and Calibration of Micrometer Screw Gauge as per this SOP.
- Quality Assurance Department: To review and approve the SOP and Annexures.
- Accountability:
Head Quality Control Department, Head Quality Assurance Department.
- Procedure:
5.1 | Safety Precautions/Instructions: | |||||||||||||||||||||||||||
5.1.1 | Wear personal protective equipments such as hand gloves during operation of micrometer screw gauge. | |||||||||||||||||||||||||||
5.2 | Operation: | |||||||||||||||||||||||||||
5.2.1 | Range of the instrument is 0 to 25 mm & least count is 0.001mm. | |||||||||||||||||||||||||||
5.2.2 | There are three scale readings on micrometer screw gauge. | |||||||||||||||||||||||||||
5.2.3 | Main scale range is 0 to 25 mm, circular scale range is 0 to 50 and coincide scale range is 0 to 10. | |||||||||||||||||||||||||||
5.2.4 | Loosen the small screw provided by pushing it right side. | |||||||||||||||||||||||||||
5.2.5 | First adjust the circular scale to the 0 reading. | |||||||||||||||||||||||||||
5.2.6 | 0 on the main scale should coincide with the 0 of circular scale reading. | |||||||||||||||||||||||||||
5.2.7 | Then carefully insert the sample into the micrometer screw gauge by rotating the circular scale knob to hold firmly. | |||||||||||||||||||||||||||
5.2.8 | First note down the reading on the main scale. | |||||||||||||||||||||||||||
5.2.9 | Then note down the reading on circular scale which is coinciding with the division on the coincide scale. | |||||||||||||||||||||||||||
5.2.10 | Calculate the thickness of the sample using the formula:
Main scale reading + (circular scale x least count) |
|||||||||||||||||||||||||||
5.2.11 | Example:
If main scale reading is 1 mm and circular scale reading coinciding is 44 then by applying formula, thickness of the sample is, 1 + (44 x 0.001) = 1.044 mm. |
|||||||||||||||||||||||||||
5.2.12 | Remove the sample and bring the instrument in its initial position. | |||||||||||||||||||||||||||
5.3 | Calibration Procedure: | |||||||||||||||||||||||||||
Frequency: Once in a year by external agency. | ||||||||||||||||||||||||||||
5.3.1 | Calibration is carried out by external agency as per SOP “Calibration of Instruments and Equipments”. | |||||||||||||||||||||||||||
5.3.2 | Refer Annexure for calibration test to be performed and acceptance criteria.
|
|||||||||||||||||||||||||||
5.3.3 | Generate the A. R. No. on the “Instrument/Equipment Calibration Register” as per SOP and give requisition to QA department for calibration formats of instruments/equipments on the due date of calibration. | |||||||||||||||||||||||||||
5.3.4 | For issuance of calibration report refer SOP “Control of documents, Preparation, Approval, Issuance and Maintenance. | |||||||||||||||||||||||||||
5.3.5 | Update “Annual Calibration Schedule” and “Monthly Calibration Schedule” as per SOP No “Calibration of Instruments and Equipments”. | |||||||||||||||||||||||||||
5.3.6 | If any breakdown occurs, follow procedure as per SOP “Calibration of Instruments and Equipments”. |
- Definitions / Abbreviations:
- Definitions:
- Breakdown: Any activity leading to operation of instrument/equipment other than the set parameters or unusual sound or vibration observed in the instrument/equipment.
- Calibration: Tests performed to ensure that the instrument/equipment is functioning as per set parameters. These tests are performed as per predefined frequency and also after any major repair or replacement of parts.
- Abbreviations:
Abbreviation | Expansion |
SOP | Standard Operating Procedure |
QC | Quality Control |
QA | Quality Assurance |
A. R. No | Analytical Reference Number |
No. | Number |
mm | millimetre |
PM | Preventive Maintenance |
*Note – Ready to use SOP available in “DOWNLOAD” Section.