SOP Title: Operation, Cleaning and Calibration of Heating Mantle

SOP Title: Operation, Cleaning and Calibration of Heating Mantle

  1. Objective:

To lay down the procedure for Operation, Cleaning and Calibration of Heating Mantle.

 

  1. Scope:

This SOP is applicable for Operation, Cleaning and Calibration of Heating Mantle located in Quality Control Laboratory.

 

  1. Responsibility:
  • Quality Control: To prepare and review the SOP. To follow the procedures laid down for Operation, Cleaning and Calibration of Heating Mantle as per this SOP.
  • Engineering Department: To carry out preventive maintenance as per schedule and procedure defined.
  • Quality Assurance Department: To review and approve the SOP and Annexures.

 

  1. Accountability:

Head Quality Control Department, Head Quality Assurance Department.

 

  1. Procedure:

 

     5.1 Safety Precautions/Instructions:
5.1.1 Ensure all the electrical connections are properly earthed. Ensure the power plug of the heating mantle is fixed in the socket properly.  
5.1.2 Wear personal protective equipments such as safety glasses, heat resistant hand gloves during operation of equipment.  
5.1.3 Ensure that the hot plate switch is working properly by switching “ON” the heating mantle.             
5.2 Operation  Procedure:
5.2.1 Check the validity of Calibration before starting any operations.  
5.2.2 Ensure that the surface of the coil is clean & dry.  
5.2.3 Switch ON the main switch of heating mantle.  
5.2.4 The red light indicator on the equipment will glow.  
5.2.5 Adjust the required temperature using the knob provided on the front side of the equipment by rotating clockwise direction.  
5.2.6 Keep the sample solution required for heating on the heating mantle.  
5.2.7 Care should be taken that the solution should not overflow on the coil.  
5.2.8 The green light indicator on the equipment will glow after attaining required temperature.  
5.2.9 After use, switch OFF the main switch and remove the sample solution from the heating mantle.  
5.3 Cleaning Procedure:
5.3.1 Switch OFF the main switch.  
5.3.2 Allow to cool and clean the outer surface with lint free cloth.  
5.4 Calibration Procedure:
  Frequency:  Once in a year by external agency or after carrying out any major maintenance work.
5.4.1 Calibration is carried out by external agency as per SOP “Calibration of Instruments and Equipments”.  
5.4.2 Refer Annexure for calibration test to be performed and acceptance criteria.

Sr. No. Tests Set value Acceptance Criteria
1. Temperature Verification 30oC ±2oC
50oC ±2oC
75oC ±2oC
90oC ±2oC
 
5.4.3 Generate the A. R. No. on the “Instrument/Equipment Calibration Register” as per SOP and give requisition to QA department for calibration formats of instruments/equipments on the due date of calibration.  
5.4.4 For issuance of calibration report refer SOP “Control of documents, Preparation, Approval, Issuance and Maintenance.  
5.4.5 If any breakdown occurs, follow procedure as per SOP “Calibration of Instruments and Equipments”.  

 

  1. Definitions /Abbreviations:
  • Definitions:
  • Breakdown: Any activity leading to operation of instrument/equipment other than the set parameters or unusual sound or vibration observed in the instrument/equipment.
  • Calibration: Tests performed to ensure that the instrument/equipment is functioning as per set parameters. These tests are performed as per predefined frequency and also after any major repair or replacement of parts.

  

  • Abbreviations:
Abbreviation Expansion
SOP Standard Operating Procedure
QC Quality Control
QA Quality Assurance
No. Number
A. R. No. Analytical Reference Number

 

*Note – Ready to use SOP available in “DOWNLOAD” Section.

 

 