SOP Title: Operation, Cleaning and Calibration of Centrifuge Apparatus

SOP Title: Operation, Cleaning and Calibration of Centrifuge Apparatus

  1. Objective:

To lay down the procedure for Operation, Cleaning and Calibration of Centrifuge Apparatus.

 

  1. Scope:

This SOP is applicable for Operation, Cleaning and Calibration of Centrifuge Apparatus located in Quality Control Laboratory.

 

  1. Responsibility:
  • Quality Control: To prepare and review the SOP. To follow the procedures laid down for Operation, Cleaning and Calibration of Centrifuge Apparatus as per this SOP.
  • Engineering Department: To carry out preventive maintenance as per schedule and procedure defined.
  • Quality Assurance Department: To review and approve the SOP and Annexures.

 

  1. Accountability:

Head Quality Control Department, Head Quality Assurance Department.

 

  1. Procedure:

 

    5.1 Safety Precautions/Instructions:
5.1.1 Ensure all the electrical connections are properly earthed. Ensure the power plug of the centrifuge apparatus is fixed in the socket properly.  
5.1.2 Ensure that the ON/OFF switch is working properly by Switching  “ON”

the centrifuge apparatus.

 
    5.2 Operation:
5.2.1 Switch ON the main switch. Red light indicator on the equipment will glow.  
5.2.2 Open the lid of centrifuge apparatus.  
5.2.3 Four-centrifuge tube stands are provided inside the equipment.  
5.2.4 Check that the centrifuge tubes are clean and dry before pouring sample solution in it.  
5.2.5 Put the centrifuge tube containing sample solution in the centrifuge apparatus.  
5.2.6 Ensure that the sample solution should not be more than 80% capacity of the centrifuge tube.  
5.2.7 Place the centrifuge tubes in such positions that the opposite sides are balanced.  
5.2.8 When using two centrifuge tubes they should be placed opposite to each other.  
5.2.9 Turn the main knob to the ‘1’ position in clockwise direction.  
5.2.10 Instrument will start at low speed (1000 rpm). Then increase the speed to position 2 (2000 rpm), 3 (4000 rpm), 4 (8000 rpm), 5 (10000 rpm) or as required.  
5.2.11 After completion, slowly decrease the speed on the knob and then finally bring to OFF position.  
5.2.12 Open the lid of centrifuge machine, remove the centrifuge tube and check for satisfactory results.  
5.2.13 Switch OFF the main switch after completion.  
5.3 Cleaning Procedure:
5.3.1 Clean the centrifuge machine externally and internally with clean lint free cloth.  
5.4 Calibration Procedure:
  Frequency:  Once in a year by external agency or after carrying out any major maintenance work.
5.4.1 Calibration is carried out by external agency as per SOP “Calibration of Instruments and Equipments”.  
5.4.2 Refer Annexure for calibration test to be performed and acceptance criteria.

Sr. No. Tests Knob Set value Acceptance Criteria

(± 5%)

1. RPM Verification 1 1000 1000 ± 50 rpm
2 2000 2000 ± 100 rpm
3 4000 4000 ± 200 rpm
4 8000 8000 ± 400 rpm
5 10000 10000 ± 500 rpm
 
5.4.3 Generate the A. R. No. on the “Instrument/Equipment Calibration Register” as per SOP and give requisition to QA department for calibration formats of instrument/equipment on the due date of calibration.  
5.4.4 For issuance of calibration report refer SOP “Control of documents, Preparation, Approval, Issuance and Maintenance.  

 

  1. Definitions / Abbreviations:

 

  • Definitions:

 

  • Breakdown: Any activity leading to operation of instrument/equipment other than the set parameters or unusual sound or vibration observed in the instrument/equipment.
  • Calibration: Tests performed to ensure that the instrument/equipment is functioning as per set parameters. These tests are performed as per predefined frequency and also after any major repair or replacement of parts.

 

  • Abbreviations:

  

Abbreviation Expansion
SOP Standard Operating Procedure
QC Quality Control
QA Quality Assurance
No. Number
A. R. No. Analytical Reference Number

 