  1. Objective:

To lay down a procedure for the Preventive Maintenance of Factory & Buildings of the site for Mechanical & Structural Impairment.

  1. Scope:

This procedure is applicable for all Buildings and Civil Structures present at site

  1. Responsibility:
    • Engineering Department: To prepare and review the SOP. To follow the procedure laid down for the maintenance of all Buildings and Civil Structures as per this SOP.
    • Head of Engineering Shall be responsible for overall compliance to the laid down procedure.

3.3 Quality Assurance Department: To review and approve the SOP and Annexures. To ensure compliance of the procedure.

 

  1. Accountability:

Head, Engineering Department / Head, Quality Assurance Department.

  1. Procedure:
    • Definitions:

5.1.1   Engineering Associate: Executive or Operator of Engineering Department trained to perform duties as per this SOP.

5.2.    Operational Procedure:              

  Requirements:
5.2.1 Inputs: Building construction materials & its related Accessories, Paints & Waterproofing.

Records: Building maintenance checklist, civil architectural/structural drawings.

 
  Safety Precautions/Instructions:
5.2.2 Wear appropriate Personal Protective Equipment like Safety shoes, Helmets, Safety belts, relevant safety permits while doing the activity.  
  Operation
5.2.3 Check the Factory and Buildings for Civil, Mechanical & Structural impairment. Prepare List of Factory and Buildings.  
5.2.4 Fill the checklist for various Buildings & Structures. Prepare Check List for Civil Maintenance of Factory & Buildings.  
5.2.5 Check the compound wall of the factory premises for:

• Steadiness

• Visible cracks

• Growth of wild plants

 
5.2.6 Check the integrity of the Waterproofing of Terraces & Gutters.  
5.2.7 Check the opening of Rain water pipes.  
5.2.8 Check the integrity of Parapet walls of terraces.  
5.2.9 Check the integrity of the Gable wall joints of the Buildings.  
5.2.10 Check that the Terraces & Gutters are clean & there is no Fungus formation.  
5.2.11 Check that the Storm water drainage channels are clean.  
5.2.12 Check the structural Pipe bridges for Integrity and Corrosion.  
5.2.13 Check the external surface of the Buildings for structural cracks or any structural impairment.  
5.2.14 Check the Fire Hydrant Line for Integrity and Corrosion.  
5.2.15 Check the Septic Tank for any cracks and available spare capacity.  
5.2.16 Check the MS powder coated Sheets/Insulation of them roofing for Pinholes, Corrosion and Integrity of J hooks.  
5.2.17 Check the chequered platforms over pipe bridges for Integrity and Corrosion.  
5.2.18 Check the cross over bridges for Integrity and Corrosion.  
5.2.19 Check the water tanks for leakages and cracks.  
5.2.20 Check the MS Railing of staircases for Steadiness and Corrosion.  
5.2.21 Check the structure of MS Staircases of the buildings for Steadiness and Corrosion.  
5.2.22 Check the stone pitching for the steadiness of Earth Embankments of the internal roads.  
5.2.23 Check the rain water pipes and net for corrosion.  
5.2.24 Instruct the Engineering Contractors to carry out the Repairs/Civil works/Paintings etc as per the checklist (if required).  
5.2.25 Inform the corrective actions taken to the Site Head.  

 

  1. Abbreviation:
Abbreviation Expansion
SOP Standard Operating Procedure
EGD Engineering Department
MS Mild Steel

 

*Note – Ready to use SOP available in “DOWNLOAD” Section.

 